Close season works for Boatfolk

 17 May 2021
Close season works for Boatfolk

We returned to Boatfolk’s Portland Marina in mid-March to continue the works begun in 2020, this time adding  to the back walkway and adding a new C pier using System 21 pontoons. The latter has 36 finger pontoons to give additional 10 and 12m berths, all fully serviced with water and electric points and it was all completed by early May. 

We also spent some time at Boatfolk’s Haslar Marina, replacing the hammerhead pontoon with a new installation built using Walcon’s high freeboard (up to 750mm from 500mm), heavy duty, Jumbo pontoons, ideal for larger boats, and at Portishead Marina in Bristol where we added 19 finger pontoons.

« Return to News